How is an apartment renovated in Kadıköy?

Process, Timescale, the Right Questions

Because our studio is in Kadıköy, we know most of the renovation enquiries in the area at first hand: mostly flats built between the 1990s and the 2000s, whose room divisions no longer suit the way people live and whose services have aged. The steps below are the general route we follow when starting on a flat of that kind.

We have written this as a neighbourhood guide: what makes renovation in Kadıköy easier and harder, the order of the process, what actually extends the programme, and the questions to ask at the first meeting.

Kadıköy’s building stock: two different renovations

Kadıköy is not one uniform district, and the logic of a renovation changes noticeably with the age of the building.

Which group a flat belongs to becomes clear in the first half hour of the site survey, and it largely determines the rest of the process.

The process, step by step

01

Survey and measurement

We first walk the flat, noting the load-bearing walls (which walls can come out), where the service runs pass and how the daylight moves through the day. This stage usually takes one or two visits.

02

Municipal and management permissions

In Kadıköy most building managements ask for written consent for work touching the shared services (risers, main pipe runs); in some buildings the hours during which the lift may be used are also restricted. The construction programme cannot be fixed until these permissions are clear — starting this step early saves the project weeks.

03

Design and material selection

The revised layout, the material palette and the lighting scheme are settled at this stage. No order is placed without the client's approval.

04

Construction

In sequence: demolition, plumbing and electrical services, plastering, floor and wall finishes, kitchen and bathroom installations, decoration and final details. Renovating a typical 100–120 m² flat from end to end takes between 8 and 14 weeks depending on scope — a surface refresh alone (decoration, flooring, kitchen) can come down to 3–5 weeks.

05

Handover

The flat is handed over after a final clean, a check of the details and a briefing on use and maintenance.

What you can change, and what you cannot

Not everything is open in a flat. What turns a renovation daydream into a realistic plan is knowing that boundary from the outset:

What to establish before demolition

Building rules set the programme

In interior projects, what usually surprises the programme is not the building work but the building's own rules. The ones we meet most often in Kadıköy: the hours within which noisy work is permitted, a ban on working at weekends, whether the lift may be used to move materials and, if so, on condition that it is protected, rubble removal confined to particular days, and a requirement to clean the common areas daily.

These rules differ from building to building, which is why we schedule the conversation with the management immediately after the survey. A constraint learned early is written into the programme; one learned late breaks it.

Is a permit required, or not?

The general framework is this: interior alterations that do not touch the load-bearing structure or the external appearance of the building are usually not subject to permit; changes to structural elements, to the façade or window frames, or works that alter the character of the unit are assessed separately. But this is a decision for the authority, not a matter of interpretation — the right course is to confirm with the relevant municipality once the scope is clear. Look at the scope of your own project, not at the categorical statements circulating online.

What extends the programme

Where the budget actually goes

We do not give figures — because any number stated without knowing the scope is a guess. But we can say where the weight of the budget falls: wet areas (the kitchen and bathrooms) carry the densest concentration of services and joinery per square metre; invisible infrastructure is a real item in older buildings; and the proportion of bespoke work and the material class together allow the same layout to be built across a wide budget range.

There is also the contingency: we recommend keeping a portion of the total in reserve for the things that cannot be seen until demolition opens them up. How the whole process runs is set out in our Process & Budget Guide, and how we work on homes on our residential interior design page. Among the work we have completed in Kadıköy you can also look at Four Winds Feneryolu and HD Law Office.

The right questions

Three questions to ask an interior architect at the first meeting: “are we touching a load-bearing wall?”, “which permissions will we need from the building management?”, and “can we go on living in the flat during the works, or do we need to move out?” These three affect both the budget and the programme more than anything else.

We would add a fourth: “will you be carrying out the construction yourselves?” On projects where design and construction sit in different hands, it becomes unclear who answers for a problem when one appears on site.

Frequently Asked Questions

How long does renovating an apartment in Kadıköy take on average?

It depends on the scope: a surface refresh takes 3–5 weeks, a full renovation including the services 8–14 weeks. Restrictions on working hours set by the building management can extend that.

Can I stay in the flat during the works?

If only surface work is under way (decoration, flooring) it is usually possible; if the plumbing and electrical installation are being replaced we would advise moving out temporarily, because of the dust, water shut-offs and noise.

Is a permit required to renovate inside a flat?

Interior alterations that do not touch the load-bearing structure or the building's façade generally do not require a permit; changes to structural elements, to the façade or window frames, or works that alter the character of the unit are assessed differently. The right course is to confirm with the relevant municipality once the scope is clear — the rules vary with the building and with the nature of the work.

Is permission needed from the building management?

For work affecting shared services, and in most buildings generally, yes. Rules on working hours, use of the lift and days for removing rubble also affect the programme directly, which is why we put the conversation with the management right at the start of the process.

Do all the services have to be replaced in an older flat?

There is no automatic answer. What decides it is the material, age and condition of the existing lines, and whether the wet areas are moving. Not renewing an old line behind a wall that is going to be opened anyway means opening that same wall again a few years later.

Can the kitchen or bathroom be moved?

Technically it is usually possible, but it is one of the most expensive decisions: the fall available on the waste pipe, the connections to the riser and the depth that can be taken up in the floor all set limits. We take that decision after seeing the drainage levels at the survey.

Continue reading